United projects at ORD
Polaris Lounge renovation
●Open Polaris lounge
United builds Opened April 29, 2025 25,000 sq ft
Reopened 50% larger at nearly 25,000 sq ft — 350+ seats, an expanded dining room, and what United says makes it the first US airline running two full-service bars in a business-class lounge. United's most recent finished lounge investment anywhere.
Satellite Concourse 1 (19 gates)
◆Under construction Gates
Joint build Target late 2028 580,000 sq ft $1.3B 19 gates
The first big piece of the $8.5B O'Hare expansion actually being built: a 580,000 sq ft satellite south of Concourse C, 19 gates convertible between 18 narrowbody and 9 widebody positions. Ground broke August 2025; foundations were ~35% done by June 2026. The City builds it; United and American fund much of it through their rates — and how the gates split between them hasn't been published.
Satellite Concourse 2
◇Announced Gates
Joint build Target unsettled — 2029 at best, 2034 in some reporting
The second satellite (~460,000 sq ft, roughly 24 gates by unofficial counts) is genuinely up in the air: Chicago's aviation chief says it proceeds only 'if enough funding remains after other work,' while one City proposal would pull it forward to 2029. Gate count and date are both soft.
O'Hare Global Terminal
◇Announced Terminal
Joint build Target unsettled — 2032 on the books, later in the city's reshuffle
The Studio Gang-designed replacement for Terminal 2 that would finally let United connect domestic and international under one roof. Announced in 2018 with a 2026 target; construction hasn't started, 2032 is the completion date on the books, and Chicago was still renegotiating sequencing with United and American as of late 2025, with scenarios running past 2033. The definitive case study in why this page distinguishes 'announced' from 'under construction.'