Tracker · United Ground Buildout

What's Changing at United's Hubs?

United is in the middle of its biggest ground-infrastructure buildout ever — new concourses, new gates, and the largest clubs it has ever opened. Here's every project at all eight hubs, with honest labels for what's under construction, what's merely announced, and what a CEO teased once at a press roundtable.

Updated Verified
Your tracker briefing
Latest: LAX's people mover slips again: contractor completion now December 8, passenger service early January 2027 — not October.
Set your home airport on The Blue Board to put its status here.
new flagship clubs in 2026
3
IAH · IAD · SFO
new club space this year
~119k
sq ft — IAH 54k + IAD 40k + SFO 25k
new gates targeted fall 2026
36
22 at IAH · 14 at IAD
largest club, once IAH opens
54,000
sq ft — DEN holds the title today

The map: where the work is

IAH IAD SFO DEN ORD EWR LAX
United building now United project announced Recently delivered Quiet right now
Hover or tap a hub for its summary — full breakdown below
Beyond the map: Quiet GUM — Tamuning

Check your hub

Hub by hub

Terminal Under construction joint build
Terminal B transformation
Target: fall 2026 · $2.55B · 22 gates

United's rebuild of 1969-vintage Terminal B: a 765,000 sq ft North Concourse with 22 new gates, a nearly doubled central processor for check-in, security and baggage claim behind ~67,000 sq ft of glass, 18 modernized South Concourse regional gates, and a new bag system. United is in for $1.9B+, the City of Houston ~$624M. The B lobby has been closed since January 2025 — B passengers check in at Terminal C until it reopens.

Sources (3) verified Sep 28, 2026
  1. Houston Airports
  2. Houston Airports
  3. Simple Flying
Club Under construction
United Club, Terminal B North
Target: by end of 2026 · 54,000 sq ft

The headliner: a 54,000 sq ft club on the new North Concourse's mezzanine — the largest in United's network and likely the largest airline-branded lounge in the country, more than 50% bigger than the Denver club that currently holds United's crown. Tied to the concourse's fall 2026 completion, so if the concourse slips, the club slips.

Sources (2) verified Sep 28, 2026
  1. The Points Guy
  2. Houston Airports
Club Fly Open
United Club Fly, Terminal B South
Opened Feb 25, 2025

United's second grab-and-go Club Fly (after Denver), near gates B12/B20: barista coffee, grab-and-go food, a charging counter — no seating, no alcohol. Built for connectors who want ten good minutes, not two loitering hours.

Sources (2) verified Sep 28, 2026
  1. United Newsroom
  2. The Points Guy
Terminal Open airport builds
International terminal redevelopment (ITRP)
Opened Feb 2026 · $1.46B

Houston Airports' own $1.46B program — not United's money, but United's international passengers live in it: the six-gate D-West pier (open since October 2024), a new international ticketing hall, and a rebuilt roadway. 'Open' here means substantially complete — the airport's stated February 2026 finish for the last item, baggage-system certification, not a ribbon-cutting.

Sources (1) verified Sep 28, 2026
  1. communityimpact.com
Terminal Under construction airport builds
Concourse E
Target: October 2026 · 435,000 sq ft · 14 gates

A 435,000 sq ft midfield concourse built by MWAA and occupied entirely by United: 14 gates sized for both narrowbody and widebody aircraft, 46,000 sq ft of concessions, and a direct AeroTrain connection. MWAA floated September in mid-July; on September 16 its board heard the opening now slips into October, after operational testing turned up issues to fix — still no exact day. The published cost keeps drifting — United's 2024 announcement said 'more than $500 million', 2026 grant coverage put phase 1 near $900M, and September coverage says $700M — so we don't print a single number.

Sources (4) verified Sep 28, 2026
  1. ffxnow.com
  2. Washington Dulles
  3. prnewswire.com
  4. ffxnow.com
Club Under construction joint build
United Club, Concourse E (flagship)
Target: October 2026 · 40,000 sq ft

United's new flagship Dulles club: ~40,000 sq ft above the AeroTrain escalators, seating around 650 — a ~70% jump in United Club space at IAD. The design riffs on L'Enfant's DC street grid ('there's no cul-de-sacs, there's no dead ends,' per United's club chief). Buffet and bar, no showers. Opens with the concourse — now expected in October 2026.

Sources (4) verified Sep 28, 2026
  1. The Points Guy
  2. ffxnow.com
  3. The Points Guy
  4. prnewswire.com
Club Announced joint build
C/D United Club renovations

The three existing C/D clubs stay open after Concourse E debuts, and United says they'll 'evolve' with renovations as the wider Dulles redevelopment progresses. No scope, budget, or timeline published — announced in the loosest sense.

Sources (1) verified Sep 28, 2026
  1. The Points Guy
Polaris Announced
Flagship Polaris lounge (master plan)

Upgraded from rumor on July 29, 2026: the officially unveiled Dulles master plan includes 'more United Club space and plans for one of the largest United Polaris lounges in the world.' No size, date, or location yet — and note the evolution: Kirby's April tease ('It'll be a big club') was a United Club; the official language is Polaris. Inside a decade-long program, 'plans for' is a direction, not a construction schedule.

Sources (2) verified Sep 28, 2026
  1. United Newsroom
  2. The Points Guy
Terminal Announced airport builds
Dulles master plan ($20B+, incl. Concourse E phase 2)
Target: phased over the next decade

Officially unveiled July 29, 2026: a more-than-$20B transformation — up from the $7B previously allocated — adding or renovating some 5 million sq ft over the next decade. Replaces the 1980s C/D concourses, expands the AeroTrain and retires the mobile lounges, adds a central walking tunnel from the Saarinen terminal, a new customs facility, more gates (Concourse E's next phase reportedly starts ~2028), and more lounge space. MWAA finances much of it through municipal bonds; phases and dates beyond Concourse E are not yet scheduled.

Sources (3) verified Sep 28, 2026
  1. United Newsroom
  2. ffxnow.com
  3. ffxnow.com
Club Announced
United Club, Terminal 2
Target: by end of 2026 · 25,000 sq ft

United's fourth and largest SFO club: 25,000 sq ft in Terminal 2 with the feature nobody else in the network has — a 4,000 sq ft heated outdoor terrace overlooking the airfield, United's biggest outdoor lounge space ever. Revealed June 2026 with renderings; 'by the end of 2026' is the only date United has put on it.

Sources (2) verified Sep 28, 2026
  1. The Points Guy
  2. Simple Flying
Terminal Under construction airport builds
Terminal 3 West modernization
Target: fall 2027 (first phase) · 650,000 sq ft · $2.6B

SFO's $2.6B seismic rebuild of the western half of United's home terminal: a new centralized checkpoint, self bag-drop, and 200,000 sq ft of added space. The traveler cost today: United's west T3 counters have moved to Terminal 2 and part of the T3 departures curb is closed into 2027. Airport-funded — United is the anchor tenant, not the builder.

Sources (2) verified Sep 28, 2026
  1. futuretravelexperience.com
  2. airportindustry-news.com
Club Open
United Club B-East
Opened Sep 2023 · 35,000 sq ft

The current title-holder: United's largest club in the network at ~35,000 sq ft — until Houston's 54,000 sq ft flagship opens and takes the crown. Still the benchmark for what United means by a 'big' club.

Sources (2) verified Sep 28, 2026
  1. prnewswire.com
  2. United Newsroom
Club Open
United Club B-West
Opened Jul 31, 2025 · 33,000 sq ft

United's fourth Denver lounge: 33,000 sq ft over two levels opposite gate B32, 600+ seats, two bars. Its opening pushed Denver to ~100,000 sq ft of United club space seating nearly 1,600 — the biggest club footprint at any hub.

Sources (2) verified Sep 28, 2026
  1. United Newsroom
  2. The Points Guy
Club Fly Open
United Club Fly, B-East
Opened Nov 2022 · 1,500 sq ft

The original grab-and-go experiment, between gates B61 and B63: about 1,500 sq ft, ~16 seats, coffee and cold food for connectors. The concept United later copied to Houston.

Sources (3) verified Sep 28, 2026
  1. upgradedpoints.com
  2. Denver International Airport
  3. prnewswire.com
Polaris Announced
Polaris Lounge Denver

Announced in May 2023 as coming 'in a couple of years' — three years on, United has said only that design work has started. No construction, no size, no date. Denver would be the seventh and final domestic Polaris lounge, planned for the A-West mezzanine. The cleanest example on this page of announced-with-a-date-that-evaporated.

Sources (2) verified Sep 28, 2026
  1. United Newsroom
  2. The Points Guy
Gates Announced airport builds
Concourse C-West extension (11 gates)
Target: timing not finalized · 400,000 sq ft · $700M · 11 gates

DEN's $700M, 11-gate westward extension of Concourse C under its Vision 100 plan. The airport says there's a 'waiting list' for the gates but hasn't said who gets them — United and Southwest are the presumed contenders. Airport project; United connection unconfirmed.

Sources (2) verified Sep 28, 2026
  1. The Points Guy
  2. thebulkheadseat.com
Terminal Under construction airport builds
Great Hall terminal overhaul
Target: end of 2027

DEN's multi-year rebuild of the main terminal — the part every United flyer touches is security: the 17-lane East Checkpoint opened in August 2025 (early and under budget), more lanes arrive late summer 2026, and the whole program wraps by end of 2027.

Sources (2) verified Sep 28, 2026
  1. Denver International Airport
  2. tsa.gov
Polaris Open
Polaris Lounge renovation
Opened Apr 29, 2025 · 25,000 sq ft

Reopened 50% larger at nearly 25,000 sq ft — 350+ seats, an expanded dining room, and what United says makes it the first US airline running two full-service bars in a business-class lounge. United's most recent finished lounge investment anywhere.

Sources (2) verified Sep 28, 2026
  1. prnewswire.com
  2. upgradedpoints.com
Gates Under construction joint build
New Concourse D (Satellite 1, 19 gates)
Target: late 2028 · 580,000 sq ft · $1.3B · 19 gates

The first big piece of the $8.8B ORDNext program actually being built: a 580,000 sq ft satellite south of Concourse C, 19 gates convertible between 18 narrowbody and 9 widebody positions. Ground broke August 2025; by August 2026 the City said its steel frame was rising and it remains on schedule for late 2028, with a guaranteed maximum price locked in June at least $21M under budget. The City builds it; United and American fund much of it through their rates — and how the gates split between them hasn't been published.

Sources (3) verified Sep 28, 2026
  1. City of Chicago
  2. news.constructconnect.com
  3. City of Chicago
Gates Announced joint build
New Concourse E (Satellite 2)
Target: 14 gates in 2030, 24 by 2034 · 24 gates

Pulled forward in August 2026: the City now breaks ground 'later this year' on a first phase of 14 gates opening in 2030, freeing room to build the Global Terminal; the last 10 gates follow in 2034, for ~460,000 sq ft west of Concourse D serving regional, narrowbody and preclearance flights. Sequencing was worked out with United and American. Until the shovels are actually in, it stays 'announced' — this is the same concourse whose funding was in doubt as recently as February.

Terminal Announced joint build
O'Hare Global Terminal
Target: built 2029–2033

The Studio Gang-designed replacement for Terminal 2 that would finally let United connect domestic and international under one roof. Announced in 2018 with a 2026 target; after a year of renegotiation with United and American, the City's August 2026 resequencing builds it in a single phase from 2029 to 2033 — a year later than the 2032 date previously on the books. Construction hasn't started. The definitive case study in why this page distinguishes 'announced' from 'under construction.'

Sources (3) verified Sep 28, 2026
  1. City of Chicago
  2. ord21.com
  3. dailyherald.com

United finished its EWR lounge portfolio in 2023 — the current construction here is the Port Authority's, not United's.

Polaris Open
Polaris Lounge dining room expansion
Opened Jun 21, 2025 · 1,500 sq ft

A dedicated 1,500 sq ft à-la-carte dining room with Manhattan skyline views, taking the Terminal C Polaris Lounge past 30,000 sq ft — the second-largest Polaris in the network, behind SFO. The most recent United-funded work at EWR; nothing newer is announced.

Sources (2) verified Sep 28, 2026
  1. One Mile at a Time
  2. The Points Guy
Gates Announced airport builds
Terminal A gate expansion

The Port Authority's record $45B 2026–2035 capital plan funds design and construction of additional Terminal A gates. To be clear about who benefits: United's hub lives in Terminal C — Terminal A hosts American, Delta, JetBlue and others — so this is airport-level capacity relief around United's operation, not new United gates. No gate count, cost, or dates have been published.

Sources (2) verified Sep 28, 2026
  1. Port Authority of NY & NJ
  2. aviationweek.com
Transit Under construction airport builds
AirTrain replacement
Target: 2030 · $3.5B

The Port Authority's $3.5B replacement of the 1996 monorail — three new stations, capacity up from ~33,000 to ~50,000 daily riders. Ground broke October 2025. For United flyers this is the biggest day-to-day construction pain at EWR between now and 2030, including extended shutdowns of the old system.

Sources (1) verified Sep 28, 2026
  1. Port Authority of NY & NJ

Quiet on United's side — its $573M Terminal 7/8 rebuild wrapped back in 2019, and LAX isn't on United's 2026 club list. What's moving here is LAWA's.

Transit Under construction airport builds
Automated People Mover (T7/T8 station)
Target: early January 2027

LAWA's 2.25-mile train to the rental-car center and Metro, with its east station serving United's Terminals 7/8. A monument to slipped dates: originally due March 2023, projected finished January 2026 by its lenders' analysts, then posted for October 2026 — and in September the contractor pushed completion to December 8, putting passenger service in early January 2027 after 30 days of testing and approvals, a date it says isn't guaranteed. It's ~99% complete, amid a July lawsuit from the contractor blaming LAWA for the delays and a grand jury report faulting the contractor. Not United's project, but it's the thing that will actually change how you get to a United flight at LAX.

Sources (3) verified Sep 28, 2026
  1. mynewsla.com
  2. crankyflier.com
  3. Los Angeles World Airports
GUM A.B. Won Pat International Tamuning, GU · 1 project

Mostly quiet. A local report of a new United Club 'nearing completion' couldn't be corroborated — the article has since vanished and neither United nor the airport has announced one.

Check-in Open
Check-in lobby refresh
Opened Dec 1, 2025

United rebuilt its Guam check-in lobby with 15 next-generation kiosks and new bag-drop lanes — checking in now takes under two minutes, United says. Announced for mid-October 2025, ribbon-cut December 1: a six-week slip even the small projects aren't immune to.

Sources (3) verified Sep 28, 2026
  1. United Newsroom
  2. guam.stripes.com
  3. mbjguam.com

All projects, one table

All tracked United hub projects
Scale Evidence
Terminal B transformation joint build IAH IAH projects → Terminal Under construction fall 2026 $2.55B · 22 gates
Sources (3) verified Sep 28, 2026
  1. Houston Airports
  2. Houston Airports
  3. Simple Flying
United Club, Terminal B North IAH IAH projects → Club Under construction by end of 2026 54,000 sq ft
Sources (2) verified Sep 28, 2026
  1. The Points Guy
  2. Houston Airports
United Club Fly, Terminal B South IAH IAH projects → Club Fly Open Feb 25, 2025 —
Sources (2) verified Sep 28, 2026
  1. United Newsroom
  2. The Points Guy
International terminal redevelopment (ITRP) airport builds IAH IAH projects → Terminal Open Feb 2026 $1.46B
Sources (1) verified Sep 28, 2026
  1. communityimpact.com
Concourse E airport builds IAD IAD projects → Terminal Under construction October 2026 435,000 sq ft · 14 gates
Sources (4) verified Sep 28, 2026
  1. ffxnow.com
  2. Washington Dulles
  3. prnewswire.com
  4. ffxnow.com
United Club, Concourse E (flagship) joint build IAD IAD projects → Club Under construction October 2026 40,000 sq ft
Sources (4) verified Sep 28, 2026
  1. The Points Guy
  2. ffxnow.com
  3. The Points Guy
  4. prnewswire.com
C/D United Club renovations joint build IAD IAD projects → Club Announced — —
Sources (1) verified Sep 28, 2026
  1. The Points Guy
Flagship Polaris lounge (master plan) IAD IAD projects → Polaris Announced — —
Sources (2) verified Sep 28, 2026
  1. United Newsroom
  2. The Points Guy
Dulles master plan ($20B+, incl. Concourse E phase 2) airport builds IAD IAD projects → Terminal Announced phased over the next decade —
Sources (3) verified Sep 28, 2026
  1. United Newsroom
  2. ffxnow.com
  3. ffxnow.com
Terminal 3 West modernization airport builds SFO SFO projects → Terminal Under construction fall 2027 (first phase) 650,000 sq ft · $2.6B
Sources (2) verified Sep 28, 2026
  1. futuretravelexperience.com
  2. airportindustry-news.com
United Club, Terminal 2 SFO SFO projects → Club Announced by end of 2026 25,000 sq ft
Sources (2) verified Sep 28, 2026
  1. The Points Guy
  2. Simple Flying
Great Hall terminal overhaul airport builds DEN DEN projects → Terminal Under construction end of 2027 —
Sources (2) verified Sep 28, 2026
  1. Denver International Airport
  2. tsa.gov
Polaris Lounge Denver DEN DEN projects → Polaris Announced — —
Sources (2) verified Sep 28, 2026
  1. United Newsroom
  2. The Points Guy
Concourse C-West extension (11 gates) airport builds DEN DEN projects → Gates Announced timing not finalized 400,000 sq ft · $700M · 11 gates
Sources (2) verified Sep 28, 2026
  1. The Points Guy
  2. thebulkheadseat.com
United Club B-East DEN DEN projects → Club Open Sep 2023 35,000 sq ft
Sources (2) verified Sep 28, 2026
  1. prnewswire.com
  2. United Newsroom
United Club B-West DEN DEN projects → Club Open Jul 31, 2025 33,000 sq ft
Sources (2) verified Sep 28, 2026
  1. United Newsroom
  2. The Points Guy
United Club Fly, B-East DEN DEN projects → Club Fly Open Nov 2022 1,500 sq ft
Sources (3) verified Sep 28, 2026
  1. upgradedpoints.com
  2. Denver International Airport
  3. prnewswire.com
New Concourse D (Satellite 1, 19 gates) joint build ORD ORD projects → Gates Under construction late 2028 580,000 sq ft · $1.3B · 19 gates
Sources (3) verified Sep 28, 2026
  1. City of Chicago
  2. news.constructconnect.com
  3. City of Chicago
New Concourse E (Satellite 2) joint build ORD ORD projects → Gates Announced 14 gates in 2030, 24 by 2034 24 gates
O'Hare Global Terminal joint build ORD ORD projects → Terminal Announced built 2029–2033 —
Sources (3) verified Sep 28, 2026
  1. City of Chicago
  2. ord21.com
  3. dailyherald.com
Polaris Lounge renovation ORD ORD projects → Polaris Open Apr 29, 2025 25,000 sq ft
Sources (2) verified Sep 28, 2026
  1. prnewswire.com
  2. upgradedpoints.com
AirTrain replacement airport builds EWR EWR projects → Transit Under construction 2030 $3.5B
Sources (1) verified Sep 28, 2026
  1. Port Authority of NY & NJ
Terminal A gate expansion airport builds EWR EWR projects → Gates Announced — —
Sources (2) verified Sep 28, 2026
  1. Port Authority of NY & NJ
  2. aviationweek.com
Polaris Lounge dining room expansion EWR EWR projects → Polaris Open Jun 21, 2025 1,500 sq ft
Sources (2) verified Sep 28, 2026
  1. One Mile at a Time
  2. The Points Guy
Automated People Mover (T7/T8 station) airport builds LAX LAX projects → Transit Under construction early January 2027 —
Sources (3) verified Sep 28, 2026
  1. mynewsla.com
  2. crankyflier.com
  3. Los Angeles World Airports
Check-in lobby refresh GUM GUM projects → Check-in Open Dec 1, 2025 —
Sources (3) verified Sep 28, 2026
  1. United Newsroom
  2. guam.stripes.com
  3. mbjguam.com

"Airport builds" marks projects funded and built by the airport authority — MWAA at Dulles, Houston Airports, Chicago's aviation department, the Port Authority at Newark, LAWA, and DEN — where United is the tenant or a funding partner, not the builder. They're tracked here because they change your trip, but the credit (and the schedule risk) belongs to the airport.

Why United is doing this

Start with the quote. Asked about lounge size at an April 2026 press roundtable, CEO Scott Kirby told reporters: "I want them to build a club that is oversized. That we look at it and say, 'That club is too big.'" He added that it keeps not happening: "I've now been told seven or eight times, 'This one is going to be the one.' It's never true." That is the buildout in one anecdote — United says it came out of the pandemic with 49% more club space than it had before 2020, and it still can't build ahead of demand.

The demand side is deliberate. Under United Next, premium seats per North American departure are up 40% since 2021, and every one of those seats comes with lounge expectations. Crowding is the metric the executives themselves use: no survey ranks it, but United's commercial chief Andrew Nocella defined success as the day the "no one-day passes" sign disappears from club doors. The squeeze also shows up in policy: membership went two-tier with higher fees in March 2025, and in April 2026 United quietly cut Polaris Lounge access for most Star Alliance partners.

Competition is real too. Delta's flagship Delta One Lounge at JFK runs about 40,000 sq ft — the number Houston's 54,000 was built to beat — and Amex keeps expanding Centurion. In the hub-lounge arms race, "largest in America" is a marketing asset with a construction schedule attached.

Who's actually paying

Read the badges carefully: much of this buildout rides on airport capital programs. MWAA is building Dulles' Concourse E; Houston is a partner on Terminal B; Chicago's aviation department builds the O'Hare satellites with airline money flowing through rates; the Port Authority owns everything moving at Newark. United's own capital is concentrated where its brand lives — the clubs — plus the lion's share of Houston's Terminal B. When an airport builds, the schedule risk is the airport's too.

The honest read

Dates slip, and teases are not commitments. The Denver Polaris Lounge was announced in May 2023 as "a couple of years" out and still has no date. The original Polaris lounge rollout missed its published schedule at every single hub. O'Hare's Global Terminal was announced in 2018 for 2026 and now reads 2033 — construction hasn't started. Kirby's "even bigger" second Dulles lounge is the live case study: teased as one sentence at an April 2026 roundtable, it graduated to the official Dulles master plan in July — as a Polaris, with still no size or date. That's why every project here carries one of four labels — open, under construction, announced, rumored — and why announced without a date is treated as a promise, not a plan.

Sidebar

Club math

  • 54,000 sq ft — the Houston club, roughly the floor area of the entire White House, and a little over a football field of playing turf. Largest airline lounge in the country when it opens.
  • ~119,000 sq ft of new club space opening in 2026 alone — more than United's entire Denver club footprint (~100,000 sq ft across four locations), which is currently the biggest at any hub.
  • 4,000 sq ft of open-air terrace at the new SFO club — about a tennis court and a half, outdoors, at an airport. United's largest-ever outdoor lounge space.
  • 650 seats in the new Dulles club — more than a 787-10 carries twice over.
The government's buildout, same airports

Seven of these eight hubs are also in the FAA's paper-to-digital flight strip rollout — the other half of the biggest infrastructure decade US aviation has had.

Modern Skies Tracker →

Quick answers

When does the new United Club at Houston (IAH) open?

United has committed to "by the end of 2026." The 54,000 sq ft club rides on the new Terminal B North Concourse, targeted for fall 2026 — if the concourse slips, the club slips.

What is the largest United Club?

Today: the ~35,000 sq ft United Club B-East in Denver. Once Houston’s Terminal B club opens, that crown moves to IAH at 54,000 sq ft — likely the largest airline-branded lounge in the country.

What is United building at Washington Dulles?

A new 14-gate, 435,000 sq ft Concourse E (built by the airports authority, occupied entirely by United) with a ~40,000 sq ft flagship United Club above the AeroTrain station — both now expected in October 2026, after a slip from late September. Behind it sits the $20B+ Dulles master plan unveiled in July 2026, a decade-long rebuild that includes plans for one of the largest United Polaris lounges in the world.

Is United building anything at LAX?

Not right now. United’s Terminal 7/8 rebuild wrapped in 2019, and LAX is not on United’s 2026 club list. The active construction at LAX is the airport’s people mover, whose east station serves United’s terminals.

When does the Denver Polaris Lounge open?

Unknown. United announced it in May 2023 as coming "in a couple of years," and as of mid-2026 has said only that design work started. No date, no size, no construction — which is why this tracker files it as announced, not under construction.

Changelog

  1. LAX's people mover slips again: contractor completion now December 8, passenger service early January 2027 — not October.
  2. Dulles Concourse E and its ~40,000 sq ft United Club slip from late September into October after operational testing turns up fixes.
  3. Chicago resequences ORDNext ($8.8B): O'Hare's new Concourse E breaks ground this fall (14 gates in 2030, 24 by 2034); the Global Terminal is built 2029–2033; Concourse D stays on track for late 2028.
  4. The $20B+ Dulles master plan goes official — a decade-long rebuild including 'plans for one of the largest United Polaris lounges in the world.' The rumored second Dulles lounge graduates to announced (and turns out to be a Polaris).
  5. Tracker first published — 8 hubs, 26 projects.
  6. United pulls 11 planned O'Hare routes after the FAA extends its ORD schedule cap through October 2027.
  7. O'Hare's annual gate shuffle lands: American wins back three gates effective October 2026, though United still nets two more than last year (one via reallocation, one bought from Spirit).
  8. SFO Terminal 2 club revealed: 25,000 sq ft with a 4,000 sq ft heated outdoor terrace — United's largest-ever outdoor lounge space.
  9. First look inside the ~40,000 sq ft Dulles Concourse E club — opening with the concourse this fall.
  10. IAD Concourse E lands a $41.8M FAA grant; MWAA says the 14-gate first phase is on track for fall.
  11. United quietly cuts Polaris Lounge access for most Star Alliance partners — the crowding fight comes to the premium side.
  12. Kirby's mandate goes on the record: 'build a club that is oversized' — and he teases a second, even bigger Dulles club (no date, no commitment).
  13. Guam check-in lobby refresh opens — six weeks behind its announced date.
  14. Denver B-West club opens: 33,000 sq ft, taking DEN to ~100,000 sq ft of United club space.
  15. Newark Polaris Lounge gets a 1,500 sq ft dining room expansion.
  16. O'Hare Polaris Lounge reopens 50% larger with the first two-bar setup in a US business-class lounge.
  17. Houston gets United's second grab-and-go Club Fly, in Terminal B South.

How this page is maintained: projects are verified against United's newsroom, airport authority releases (MWAA, Houston Airports, Chicago DOA, Port Authority, LAWA, DEN), and the frequent-flyer trade press. Every project in the underlying dataset cites at least one source. Sizes, costs, and dates appear only where a source supports them; disputed figures are explained in prose instead of printed as facts. Updated monthly, or when United opens or announces something.